Just installed Studio 2019 and took a peek. I have a few questions:

  1. Do translation memories used in Studio 2017 need any upgrading to ver. 2019?
  2. Can I open the 2017 project templates directly in 2019 or will it break them? (I understand that I can use the migration utility to migrate them).
  3. Can I open projects created in Studio 2017 in Studio 2019 or will it break them? WIll they be backward-compatible if I open and save them in Studio 2019?

Thanks,

Piotr

Parents
  • Hi  

    Piotr Bienkowski said:
    Do translation memories used in Studio 2017 need any upgrading to ver. 2019?

    No

    Piotr Bienkowski said:
    Can I open the 2017 project templates directly in 2019 or will it break them? (I understand that I can use the migration utility to migrate them).

    You can't use the project migration utility to migrate templates.  It's always a good idea to recreate your templates because otherwise you potentially introduce legacy problems into the newer product.  There are also new features between versions and if you use the old template you create projects without access to the latest stuff.

    Piotr Bienkowski said:
    Can I open projects created in Studio 2017 in Studio 2019 or will it break them? WIll they be backward-compatible if I open and save them in Studio 2019?

    Yes you can. But as you can use Studio 2017 for as long as you like this time around it makes sense to finish them off in 2017 and start new ones in 2019.

    Paul Filkin | RWS

    Design your own training!
    You've done the courses and still need to go a little further, or still not clear? 
    Tell us what you need in our Community Solutions Hub

Reply
  • Hi  

    Piotr Bienkowski said:
    Do translation memories used in Studio 2017 need any upgrading to ver. 2019?

    No

    Piotr Bienkowski said:
    Can I open the 2017 project templates directly in 2019 or will it break them? (I understand that I can use the migration utility to migrate them).

    You can't use the project migration utility to migrate templates.  It's always a good idea to recreate your templates because otherwise you potentially introduce legacy problems into the newer product.  There are also new features between versions and if you use the old template you create projects without access to the latest stuff.

    Piotr Bienkowski said:
    Can I open projects created in Studio 2017 in Studio 2019 or will it break them? WIll they be backward-compatible if I open and save them in Studio 2019?

    Yes you can. But as you can use Studio 2017 for as long as you like this time around it makes sense to finish them off in 2017 and start new ones in 2019.